Project 19-17
Hinckley, OH
The Hinckley Lake Dam Modification Project was designed to address the Ohio Department of Natural Resources (ODNR) Dam Safety Regulations.
The modifications included adding 10 feet of thickness to the concrete spillway. The training walls have been replaced with taller, thicker, tied-back cast-in-place walls. A new control tower has been added to the west end of the spillway. And the earthen dam has been heightened with added drainage systems built in.
he project included the placement of more than 3,000 cubic yards of structural concrete to the original spillway, along with over 10,000 cubic yards of embankment improvements to the earthen dams. Construction of the new spillway and earthen dams was successfully completed, followed by the removal of more than 15,000 cubic yards of accumulated silt from Hinckley Lake during the summer of 2025, restoring capacity and extending the service life of the infrastructure.
AWARDS
2025 ASDSO Regional Dam Safety Award (Midwest)
Presented by the Association of State Dam Safety Officials
2024 Ohio Concrete Project of the Year Award (Northeast Region)
Hinckley Lake Dam Restoration Helps Mitigate Flooding
March 26, 2024 - Midwest Edition #7
Cindy Riley - CEG Correspondent
For almost a century, the Hinckley Lake Dam has served area residents by providing recreation and helping mitigate flooding. Now, crews in Cleveland, Ohio, are performing a complete restoration of the historic barrier.
Continue reading HERE