Menu Close

Mill Creek Expressway Phase 5B

Ohio DOT’s Mill Creek Expressway Project Phase 5B Nears Early Completion, Months Ahead of Schedule

CONSTRUCTION DIGEST

by: Nathan Medcalf

A major phase of Ohio’s Mill Creek Expressway (MCE) projects is months ahead of schedule. The general contractor for this phase — The Great Lakes Construction Co. — plans to complete the self-perform work and put traffic in its final configuration at the end of 2024 — a full five months early.

“We anticipate finishing all contract work in summer 2025, prior to the September 1, 2025, completion milestone,” said Tom Hackett, DB Project Manager, The Great Lakes Construction Co. READ MORE HERE ...

ODOT Project 3000-20
Mill Creek Expressway Phase 5B
Cincinnati, OH

All 15 deck pours are complete on the Mill Creek Expressway Phase 5B Project. The team is nearing the end of Phase 6. Final Configuration is scheduled to commence this November keeping the overall project on schedule to be completed by winter 2025/2026.