Project 355-21
Cleveland, OH
Pearl & Jennings Storage Tank and Pump Station Improvements for the Northeast Ohio Regional Sewer District (NEORSD) have been completed. Great Lakes obtained Substantial Completion on April 30, 2025, with the operational demonstration of the fully automated new 1-million-gallon storage tank/shaft being online and verification of communications with the newly renovated Pump Station. During heavy rain (1/4”+ per hour), excess combined sewer/storm flow is diverted to a 1-million-gallon storage tank to prevent untreated discharge to Big Creek. Once the storm subsides, the stored flow is pumped back for treatment to the Southerly Wastewater Treatment Plant.