Project 450-23
Sandusky, OH
The Sandusky Water Pollution Control Plant (WPCP) High-Rate Treatment (HRT) Project is quickly approaching the commissioning phase. The team has been working on completing the building mechanical and electrical work in preparation for startup of the new HRT Facility and the rehabilitated screens building. Additionally, they are preparing for pavement and landscaping around these areas, which is scheduled for completion this fall. The Great Lakes project team, with support from our subcontractors and vendors, and in coordination with the City and the Engineer, look forward to putting the new and rehabilitated facilities into full-time operation and turning over to the City by the end of the year.