Project 558-24
Cleveland, OH
Earlier this year, Great Lakes launched a six-phase bulkhead replacement project at the United States Coast Guard Station in downtown Cleveland. Utilizing our newly acquired 275-ton crane, the team is installing over 45,000 square feet of sheet piling, following a design that draws its strength and stability from tie-rod connections to a secondary “deadman” wall. As phase three progresses, the team is finishing work on the east bulkhead wall and transitioning into work on the east deadman wall and its associated tie-rod connections.